nerdexam
PMIPMI

PMI-RMP · Question #294

PMI-RMP Question #294: Real Exam Question with Answer & Explanation

The correct answer is A: Document the new risks and continue the Plan Risk Responses process.. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST thing for the project manager to do?

Options

  • ADocument the new risks and continue the Plan Risk Responses process.
  • BMake sure the project work is better understood.
  • CSpend more time making sure the risk responses are clearly defined.
  • DGet more people involved in the Identify Risks process since risks have been missed.

Topics

#Secondary Risks#Risk Response Planning#Risk Identification#Iterative Risk Management

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions