PMIPMI
PMI-RMP · Question #294
PMI-RMP Question #294: Real Exam Question with Answer & Explanation
The correct answer is A: Document the new risks and continue the Plan Risk Responses process.. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the BEST thing for the project manager to do?
Options
- ADocument the new risks and continue the Plan Risk Responses process.
- BMake sure the project work is better understood.
- CSpend more time making sure the risk responses are clearly defined.
- DGet more people involved in the Identify Risks process since risks have been missed.
Topics
#Secondary Risks#Risk Response Planning#Risk Identification#Iterative Risk Management
Community Discussion
No community discussion yet for this question.