nerdexam
PMIPMI

PMI-RMP · Question #286

PMI-RMP Question #286: Real Exam Question with Answer & Explanation

The correct answer is B: Your customer has approved a change request broadening the project scope and increasing. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Which of the following events would result in a baseline update?

Options

  • AYour project is behind schedule and you want your baseline to reflect estimated actual
  • BYour customer has approved a change request broadening the project scope and increasing
  • COne of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.
  • DOne of your key project team resources has left your team and no replacement is available.

Topics

#Baseline Management#Change Control#Scope Management#Integrated Change Control

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions