PMIPMI
PMI-RMP · Question #286
PMI-RMP Question #286: Real Exam Question with Answer & Explanation
The correct answer is B: Your customer has approved a change request broadening the project scope and increasing. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
Which of the following events would result in a baseline update?
Options
- AYour project is behind schedule and you want your baseline to reflect estimated actual
- BYour customer has approved a change request broadening the project scope and increasing
- COne of the risks identified in the Risk Management Plan occurs resulting in a schedule delay.
- DOne of your key project team resources has left your team and no replacement is available.
Topics
#Baseline Management#Change Control#Scope Management#Integrated Change Control
Community Discussion
No community discussion yet for this question.