nerdexam
PMIPMI

PMI-RMP · Question #285

PMI-RMP Question #285: Real Exam Question with Answer & Explanation

The correct answer is C: Secondary risk. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. One of the risks you identified occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response you implemented. What type of risk is this called?

Options

  • AResidual risk
  • BMitigated risk
  • CSecondary risk
  • DTrigger risk

Topics

#Secondary risks#Risk response implementation#Risk classification

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions