PMIPMI
PMI-RMP · Question #285
PMI-RMP Question #285: Real Exam Question with Answer & Explanation
The correct answer is C: Secondary risk. See the full explanation below for the reasoning.
Risk Monitoring and Reporting
Question
You are a project manager working on a software development project. You've developed the risk management plan, identified risks, and determined risk responses for the risks. One of the risks you identified occurs, and you implement the response for that risk. Then, another risk occurs as a result of the response you implemented. What type of risk is this called?
Options
- AResidual risk
- BMitigated risk
- CSecondary risk
- DTrigger risk
Topics
#Secondary risks#Risk response implementation#Risk classification
Community Discussion
No community discussion yet for this question.