PMI-RMP · Question #246
You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you creat
The correct answer is C. Resource breakdown structure. A Resource Breakdown Structure (RBS) is a hierarchical decomposition of project resources organized by category and type (e.g., human resources, equipment, materials). It provides a visual diagram of all resources that will be used in the project. A Roles and Responsibility Matri
Question
You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you create to accomplish the task?
Options
- ARoles and responsibility matrix
- BWork breakdown structure
- CResource breakdown structure
- DRACI chart
How the community answered
(43 responses)- A5% (2)
- B2% (1)
- C93% (40)
Explanation
A Resource Breakdown Structure (RBS) is a hierarchical decomposition of project resources organized by category and type (e.g., human resources, equipment, materials). It provides a visual diagram of all resources that will be used in the project. A Roles and Responsibility Matrix (A) maps roles to deliverables but does not depict resources in a breakdown structure. A Work Breakdown Structure (B) decomposes project scope/deliverables, not resources. A RACI chart (D) is a type of responsibility assignment matrix showing who is Responsible, Accountable, Consulted, and Informed - it focuses on responsibility, not resource categories.