PMI-RMP · Question #246

You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you creat

The correct answer is C. Resource breakdown structure. A Resource Breakdown Structure (RBS) is a hierarchical decomposition of project resources organized by category and type (e.g., human resources, equipment, materials). It provides a visual diagram of all resources that will be used in the project. A Roles and Responsibility Matri

Risk Strategy and Planning

Question

You work as a project manager for BlueWell Inc. You want to create a visual diagram, which can depict the resources that will be used within the project. Which of the following diagrams will you create to accomplish the task?

Options

  • ARoles and responsibility matrix
  • BWork breakdown structure
  • CResource breakdown structure
  • DRACI chart

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    93% (40)

Explanation

A Resource Breakdown Structure (RBS) is a hierarchical decomposition of project resources organized by category and type (e.g., human resources, equipment, materials). It provides a visual diagram of all resources that will be used in the project. A Roles and Responsibility Matrix (A) maps roles to deliverables but does not depict resources in a breakdown structure. A Work Breakdown Structure (B) decomposes project scope/deliverables, not resources. A RACI chart (D) is a type of responsibility assignment matrix showing who is Responsible, Accountable, Consulted, and Informed - it focuses on responsibility, not resource categories.

Topics

#Resource Breakdown Structure#Resource Planning#Project Documents#Resource Management