PMI-RMP · Question #239

PMI-RMP Question #239: Real Exam Question with Answer & Explanation

The correct answer is A: Root cause analysis. See the full explanation below for the reasoning.

Risk Process Facilitation

Question

You are the project manager of the GYH project for your organization. Management has asked you to begin identifying risks and to use an information gathering technique. Which one of the following risk identification approaches is an information gathering technique?

Options

  • ARoot cause analysis
  • BAssumptions analysis
  • CSWOT analysis
  • DDocumentation reviews

Topics

#Risk Identification#Information Gathering#Root Cause Analysis#Risk Identification Techniques