PMI-RMP · Question #227
You are the project manager for the NHH project. You are working with your project team to examine the project from four different defined perspectives to increase the breadth of identified risks by…
The correct answer is B. SWOT analysis. SWOT analysis is the risk identification technique that examines a project from four defined perspectives - Strengths, Weaknesses, Opportunities, and Threats - specifically to surface internally generated risks alongside external ones.
Question
You are the project manager for the NHH project. You are working with your project team to examine the project from four different defined perspectives to increase the breadth of identified risks by including internally generated risks. What risk identification approach are you using in this example?
Options
- ARoot cause analysis
- BSWOT analysis
- CInfluence diagramming techniques
- DAssumptions analysis
How the community answered
(48 responses)- A2% (1)
- B94% (45)
- C4% (2)
Why each option
SWOT analysis is the risk identification technique that examines a project from four defined perspectives - Strengths, Weaknesses, Opportunities, and Threats - specifically to surface internally generated risks alongside external ones.
Root cause analysis starts from an already-identified risk or problem and traces backward to find its underlying cause; it does not examine the project from four forward-looking strategic perspectives.
SWOT analysis is a structured technique that evaluates the project across four defined perspectives: internal Strengths and Weaknesses, and external Opportunities and Threats. The PMBOK Guide specifically highlights that SWOT broadens the scope of identified risks by ensuring internally generated risks (from strengths and weaknesses) are captured alongside externally driven risks.
Influence diagramming represents causal relationships and dependencies between project variables graphically; it does not use four defined strategic viewpoints to generate risk identification.
Assumptions analysis tests the validity and stability of planning assumptions to expose risk from faulty assumptions; it is not a four-perspective strategic framework.
Concept tested: SWOT analysis for risk identification breadth
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.