nerdexam
PMIPMI

PMI-RMP · Question #210

PMI-RMP Question #210: Real Exam Question with Answer & Explanation

The correct answer is C: Crashing the project. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You work as a project manager for BlueWell Inc. Your project is running late and you must respond to the risk. Which risk response can you choose that will also cause you to update the human resource management plan?

Options

  • ATeaming agreements
  • BTransference
  • CCrashing the project
  • DFast tracking the project

Topics

#Risk response strategies#Schedule compression#Crashing#Human resource management plan

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions