nerdexam
PMIPMI

PMI-RMP · Question #199

PMI-RMP Question #199: Real Exam Question with Answer & Explanation

The correct answer is A: Preventive action. See the full explanation below for the reasoning.

Risk Monitoring and Reporting

Question

Beth is a project team member on the JHG Project. Beth has added extra features to the project and this has introduced new risks to the project work. The project manager of the JHG project elects to remove the features Beth has added. The process of removing the extra features to remove the risks is called what?

Options

  • APreventive action
  • BCorrective action
  • CScope creep
  • DDefect repair

Topics

#Preventive action#Risk response#Scope management#Risk mitigation

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions