PMIPMI
PMI-RMP · Question #198
PMI-RMP Question #198: Real Exam Question with Answer & Explanation
The correct answer is A: Negative $26,000. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will cost the project $65,000 if the risk happens. What is the expected monetary value of this risk event?
Options
- ANegative $26,000
- BNegative $67,000
- CZero - the risk event has not yet occurred
- D$27,000
Topics
#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Impact#Risk Probability
Community Discussion
No community discussion yet for this question.