nerdexam
PMIPMI

PMI-RMP · Question #198

PMI-RMP Question #198: Real Exam Question with Answer & Explanation

The correct answer is A: Negative $26,000. See the full explanation below for the reasoning.

Perform Targeted Risk Analysis

Question

Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will cost the project $65,000 if the risk happens. What is the expected monetary value of this risk event?

Options

  • ANegative $26,000
  • BNegative $67,000
  • CZero - the risk event has not yet occurred
  • D$27,000

Topics

#Expected Monetary Value (EMV)#Quantitative Risk Analysis#Risk Impact#Risk Probability

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions