PMI-RMP · Question #198
Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will…
The correct answer is A. Negative $26,000. Expected Monetary Value (EMV) is calculated as: EMV = Probability × Impact. Here: EMV = 0.40 × $65,000 = $26,000. Because this is a negative risk (a threat that will cost money), the EMV is expressed as negative $26,000. EMV represents the weighted average outcome, accounting…
Question
Harry works as a project manager for the NHQ Project. He is performing quantitative risk analysis for his project. One of the project risks has a 40 percent probability of happening, and it will cost the project $65,000 if the risk happens. What is the expected monetary value of this risk event?
Options
- ANegative $26,000
- BNegative $67,000
- CZero - the risk event has not yet occurred
- D$27,000
How the community answered
(23 responses)- A74% (17)
- B13% (3)
- C9% (2)
- D4% (1)
Explanation
Expected Monetary Value (EMV) is calculated as: EMV = Probability × Impact. Here: EMV = 0.40 × $65,000 = $26,000. Because this is a negative risk (a threat that will cost money), the EMV is expressed as negative $26,000. EMV represents the weighted average outcome, accounting for the likelihood the event may not occur at all. Option B ($67,000) is incorrect arithmetic. Option C (zero) is wrong - EMV is a probabilistic forecast, not an actual occurrence tracking metric. Option D ($27,000) uses incorrect rounding. EMV is used in decision trees and quantitative risk analysis to compare response options and build contingency reserves.
Topics
Community Discussion
No community discussion yet for this question.