PMI-RMP · Question #196
PMI-RMP Question #196: Real Exam Question with Answer & Explanation
The correct answer is D: Qualitative risk analysis. See the full explanation below for the reasoning.
Perform Targeted Risk Analysis
Question
You and your project team have identified the project risks and now are analyzing the probability and impact of the risks. What type of analysis of the risks provides a quick and high-level review of each identified risk event?
Options
- AA risk probability-impact matrix
- BQuantitative risk analysis
- CSeven risk responses
- DQualitative risk analysis
Topics
#Qualitative risk analysis#Risk assessment#Risk prioritization#Risk analysis