PMIPMI
PMI-RMP · Question #191
PMI-RMP Question #191: Real Exam Question with Answer & Explanation
The correct answer is B: The project scope statement will reveal the type of project as either a recurrent or first-of-its- kind project.. See the full explanation below for the reasoning.
Risk Process Facilitation
Question
Tom is the project manager of the GGG project for his company. He is working with the project team on the Perform Qualitative Risk Analysis process. Tom is having the project team to review the project scope statement as an input to the qualitative risk analysis process. Why?
Options
- AThe project scope statement must be understood to see the project requirements and the inherent risks of
- BThe project scope statement will reveal the type of project as either a recurrent or first-of-its- kind project.
- CThe project scope identifies the risks associated with project constraints.
- DThe project scope statement must be reviewed to understand the quality requirements and the risks
Topics
#Qualitative Risk Analysis#Project Scope Statement#Project Type#Inputs to Risk Analysis
Community Discussion
No community discussion yet for this question.