nerdexam
PMI

PMI-RMP · Question #191

Tom is the project manager of the GGG project for his company. He is working with the project team on the Perform Qualitative Risk Analysis process. Tom is having the project team to review the projec

The correct answer is B. The project scope statement will reveal the type of project as either a recurrent or first-of-its- kind project.. The project scope statement is reviewed during Perform Qualitative Risk Analysis because it reveals whether a project is a first-of-its-kind (unique, novel) or a recurrent (repetitive, familiar) type. First-of-its-kind projects carry significantly more uncertainty and inherent ri

Risk Process Facilitation

Question

Tom is the project manager of the GGG project for his company. He is working with the project team on the Perform Qualitative Risk Analysis process. Tom is having the project team to review the project scope statement as an input to the qualitative risk analysis process. Why?

Options

  • AThe project scope statement must be understood to see the project requirements and the inherent risks of
  • BThe project scope statement will reveal the type of project as either a recurrent or first-of-its- kind project.
  • CThe project scope identifies the risks associated with project constraints.
  • DThe project scope statement must be reviewed to understand the quality requirements and the risks

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    90% (43)
  • C
    2% (1)
  • D
    6% (3)

Explanation

The project scope statement is reviewed during Perform Qualitative Risk Analysis because it reveals whether a project is a first-of-its-kind (unique, novel) or a recurrent (repetitive, familiar) type. First-of-its-kind projects carry significantly more uncertainty and inherent risk because there is little historical data or prior experience to draw from. A recurrent project, by contrast, benefits from lessons learned and established patterns. Understanding this distinction helps the team calibrate how aggressively to assess and manage risks. Option A is partially true but too generic; option C is incorrect because constraints are typically identified earlier; option D conflates quality requirements with scope, which is not the primary reason for this review.

Topics

#Qualitative Risk Analysis#Project Scope Statement#Project Type#Inputs to Risk Analysis

Community Discussion

No community discussion yet for this question.

Full PMI-RMP Practice