nerdexam
PMIPMI

PMI-RMP · Question #185

PMI-RMP Question #185: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #185. The question stem and answer options stay visible for context.

Risk Strategy and Planning

Question

Diana is the project manager of the QPS project for her company. In this project Diana and the project team have identified a pure risk. Diana and the project team decided, along with the key stakeholders, to remove the pure risk from the project by changing the project plan altogether. What is a pure risk?

Options

  • AIt is a risk event that is generated due to errors or omission in the project work.
  • BIt is a risk event that is created by a risk response.
  • CIt is a risk event that only has a negative side, such as loss of life or limb.
  • DIt is a risk event that cannot be avoided because of the order of the work.

Unlock PMI-RMP to see the answer

You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Pure Risk#Risk Classification#Risk Definition
Full PMI-RMP PracticeBrowse All PMI-RMP Questions