PMIPMI
PMI-RMP · Question #158
PMI-RMP Question #158: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-RMP to reveal the answer and full explanation for question #158. The question stem and answer options stay visible for context.
Risk Strategy and Planning
Question
You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.
Options
- ABecause of work that was omitted during the WBS creation
- BBecause of new work generated by the risk responses
- CBecause of risk responses that are now activities
- DBecause of risks associated with work packages
Unlock PMI-RMP to see the answer
You've previewed enough free PMI-RMP questions. Unlock PMI-RMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Response Planning#WBS Updates#Project Scope#New Work Packages