During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested. What…
The correct answer is A. Work with the agile team and product owner to agree on the definition of done. The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment. If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead…
Question
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested. What should the agile practitioner do?
Options
- AWork with the agile team and product owner to agree on the definition of done
- BAsk the project sponsor to determine whether the product is completed
- CPlan another review after the product has been tested
- DAdd testing to the backlog, and have the product owner reprioritize
How the community answered
(49 responses)- A80% (39)
- B12% (6)
- C6% (3)
- D2% (1)
Explanation
The Definition of Done creates transparency by providing everyone a shared understanding of what work was completed as part of the Increment. If a Product Backlog item does not meet the Definition of Done, it cannot be released or even presented at the Sprint Review. Instead, it returns to the Product Backlog for future consideration.