PMI-ACP · Question #600
An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work. What metrics should the team use to…
The correct answer is A. Lead time, throughput, and due date performance. Lead time, throughput, and due date performance are the core flow-based performance metrics native to Kanban. Lead time measures the elapsed time from when a work item is requested to when it is delivered. Throughput measures how many items are completed per unit of time. Due…
Question
An agile project manager is planning the initial scope, schedule, and cost range estimates on a new project. The team will be using Kanban to control work. What metrics should the team use to measure performance?
Options
- ALead time, throughput, and due date performance
- BWork in progress limits, Kanban board, and time boxes
- CWork item types, sprint cadences, and defect classes
- DBurndown charts, scatter diagrams, and throughput
How the community answered
(30 responses)- A80% (24)
- B13% (4)
- C3% (1)
- D3% (1)
Explanation
Lead time, throughput, and due date performance are the core flow-based performance metrics native to Kanban. Lead time measures the elapsed time from when a work item is requested to when it is delivered. Throughput measures how many items are completed per unit of time. Due date performance measures whether items are completed by their target dates. WIP limits and Kanban boards (B) are Kanban tools and practices, not performance metrics. Sprint cadences (C) are a Scrum concept. Burndown charts (D) are a Scrum artifact and not a native Kanban metric.