PMI-ACP · Question #460
A new Sprint starts immediately following the previous Sprint.
The correct answer is A. True. According to the Scrum Guide, a new Sprint starts immediately after the conclusion of the previous Sprint - there is no gap or break between Sprints. This continuous cadence ensures consistent delivery rhythm, maintains team momentum, and prevents the team from reverting to…
Question
A new Sprint starts immediately following the previous Sprint.
Options
- ATrue
- BFalse
How the community answered
(28 responses)- A93% (26)
- B7% (2)
Explanation
According to the Scrum Guide, a new Sprint starts immediately after the conclusion of the previous Sprint - there is no gap or break between Sprints. This continuous cadence ensures consistent delivery rhythm, maintains team momentum, and prevents the team from reverting to non-Scrum behaviors during idle periods. The Sprint Review and Sprint Retrospective of one Sprint flow directly into the Sprint Planning of the next.
Topics
Community Discussion
No community discussion yet for this question.