Sprints lengths can vary each Sprint as long as they don't exceed a month.
The correct answer is A. True. According to the Scrum Guide, Sprints must be one month or less, but there is no rule mandating that every Sprint must be the same fixed duration. Teams may adjust Sprint length between Sprints (e.g., from 2 weeks to 3 weeks) as long as no single Sprint exceeds one calendar…
Question
Sprints lengths can vary each Sprint as long as they don't exceed a month.
Options
- ATrue
- BFalse
How the community answered
(40 responses)- A95% (38)
- B5% (2)
Explanation
According to the Scrum Guide, Sprints must be one month or less, but there is no rule mandating that every Sprint must be the same fixed duration. Teams may adjust Sprint length between Sprints (e.g., from 2 weeks to 3 weeks) as long as no single Sprint exceeds one calendar month. The hard constraint is the one-month maximum, not uniformity across Sprints.