PMI-ACP · Question #463
All of the following are true about change during a Sprint EXCEPT:
The correct answer is A. Changes can be made that impact the Sprint goal. The Sprint Goal is locked once a Sprint begins - it cannot be changed or undermined mid-Sprint. This makes option A the false statement (the exception). The other options are true: the Development Team freely adjusts tasks in the Sprint Backlog (B), the Product Owner controls…
Question
All of the following are true about change during a Sprint EXCEPT:
Options
- AChanges can be made that impact the Sprint goal
- BThe development team can change tasks in the Sprint backlog.
- CThe Product Owner is the only person that can add or remove a User Story in the Sprint Backlog
- DChange may occur as scope is clarified between the Product Owner and the Development Team
How the community answered
(39 responses)- A87% (34)
- B3% (1)
- C8% (3)
- D3% (1)
Explanation
The Sprint Goal is locked once a Sprint begins - it cannot be changed or undermined mid-Sprint. This makes option A the false statement (the exception). The other options are true: the Development Team freely adjusts tasks in the Sprint Backlog (B), the Product Owner controls User Story additions/removals (C), and scope clarification between the PO and Development Team is an expected, healthy practice (D).