PMI-ACP · Question #459
Which one of the following is NOT a Scrum Event?
The correct answer is D. Weekly Status. The five official Scrum Events are: the Sprint (the container event), Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. A 'Weekly Status' meeting is a traditional project management practice, not a Scrum event. In fact, Scrum discourages adding meetings…
Question
Which one of the following is NOT a Scrum Event?
Options
- ASprint
- CSprint Review
- DWeekly Status
- EThey are all Scrum events.
How the community answered
(31 responses)- C3% (1)
- D90% (28)
- E6% (2)
Explanation
The five official Scrum Events are: the Sprint (the container event), Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. A 'Weekly Status' meeting is a traditional project management practice, not a Scrum event. In fact, Scrum discourages adding meetings outside its defined events - additional meetings are considered waste unless truly necessary.
Topics
Community Discussion
No community discussion yet for this question.