The correct answer is C: Project Manager. Scrum defines exactly three roles: Product Owner, Scrum Master, and Development Team (members). There is no Project Manager role in Scrum. The traditional PM responsibilities are distributed across these roles — the Product Owner manages the backlog and priorities, the Scrum Ma
Question
Which is NOT a Scrum Role?
Options
- AProduct Owner
- BTeam Member
- CProject Manager
- DScrum Master
Explanation
Scrum defines exactly three roles: Product Owner, Scrum Master, and Development Team (members). There is no Project Manager role in Scrum. The traditional PM responsibilities are distributed across these roles — the Product Owner manages the backlog and priorities, the Scrum Master removes impediments, and the team self-organizes.