The correct answer is C: Project Manager. Scrum defines exactly three roles: Product Owner, Scrum Master, and Development Team (members). There is no Project Manager role in Scrum. The traditional PM responsibilities are distributed across these roles — the Product Owner manages the backlog and priorities, the Scrum Ma

Submitted by haruto_sh· Apr 18, 2026Agile Principles and Mindset

Question

Which is NOT a Scrum Role?

Options

  • AProduct Owner
  • BTeam Member
  • CProject Manager
  • DScrum Master

Explanation

Scrum defines exactly three roles: Product Owner, Scrum Master, and Development Team (members). There is no Project Manager role in Scrum. The traditional PM responsibilities are distributed across these roles — the Product Owner manages the backlog and priorities, the Scrum Master removes impediments, and the team self-organizes.

Topics

#Scrum Roles#Scrum Framework#Agile Roles

Community Discussion

No community discussion yet for this question.

Full PMI-ACP PracticeBrowse All PMI-ACP Questions