PMI-ACP · Question #226
PMI-ACP Question #226: Real Exam Question with Answer & Explanation
The correct answer is A: 2 sessions ?8 hours. Per the Scrum Guide, Sprint Planning for a one-month Sprint is time-boxed to a maximum of 8 hours. It is often split into two parts: Part 1 focuses on 'What' can be delivered (selecting backlog items), and Part 2 focuses on 'How' the team will do the work. Shorter sprints use pro
Question
For a one month Sprint, what is the recommended duration of the Sprint Planning meeting?
Options
- A2 sessions ?8 hours
- B1 Session ?4 hours
- C3 hours
- DDecided by the Team
Explanation
Per the Scrum Guide, Sprint Planning for a one-month Sprint is time-boxed to a maximum of 8 hours. It is often split into two parts: Part 1 focuses on 'What' can be delivered (selecting backlog items), and Part 2 focuses on 'How' the team will do the work. Shorter sprints use proportionally shorter planning sessions.
Topics
Community Discussion
No community discussion yet for this question.