PMI-ACP · Question #224
Which one is NOT a Pillar of Scrum?
The correct answer is D. Empiricism. The three pillars of Scrum are Transparency, Inspection, and Adaptation. Empiricism is the underlying theory or philosophy that Scrum is built upon - the idea that knowledge comes from experience and decisions are made based on observation. It is the foundation, not one of the th
Submitted by joshua94· Apr 18, 2026Agile Principles and Mindset
Question
Which one is NOT a Pillar of Scrum?
Options
- ATransparency
- BInspection
- CAdaption
- DEmpiricism
How the community answered
(50 responses)- A4% (2)
- C2% (1)
- D94% (47)
Explanation
The three pillars of Scrum are Transparency, Inspection, and Adaptation. Empiricism is the underlying theory or philosophy that Scrum is built upon - the idea that knowledge comes from experience and decisions are made based on observation. It is the foundation, not one of the three pillars themselves.
Topics
#Scrum Framework#Scrum Pillars#Empiricism#Agile Principles