PK0-005 · Question #79
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager…
The correct answer is A. Time and materials contract. A time and materials contract is a type of contract where the contractor is paid for the time they spend working on the project and the materials they use. This type of contract is often used for short-term projects where the duration and cost cannot be accurately estimated in…
Question
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
Options
- ATime and materials contract
- BMaster service agreement
- CFixed-price contract
- DStatement of work
- ECost-plus agreement
How the community answered
(55 responses)- A71% (39)
- B16% (9)
- C7% (4)
- D2% (1)
- E4% (2)
Explanation
A time and materials contract is a type of contract where the contractor is paid for the time they spend working on the project and the materials they use. This type of contract is often used for short-term projects where the duration and cost cannot be accurately estimated in advance.