In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

The correct answer is C. Notify the functional manager that resources are released. In a functional organization, employees are assigned to projects on a temporary basis. When a project is completed, the employees are released back to their functional manager. The project manager is responsible for notifying the functional manager that the resources are…

Project Management Concepts

Question

In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?

Options

  • AAssemble a new project with existing resources.
  • BObtain the final report from release management.
  • CNotify the functional manager that resources are released.
  • DAllocate resources in a different project.

How the community answered

(20 responses)
  • A
    15% (3)
  • B
    5% (1)
  • C
    75% (15)
  • D
    5% (1)

Explanation

In a functional organization, employees are assigned to projects on a temporary basis. When a project is completed, the employees are released back to their functional manager. The project manager is responsible for notifying the functional manager that the resources are available.

Topics

#Project Closure#Functional Organization#Resource Management#Project Manager Role