PK0-005 · Question #77

PK0-005 Question #77: Real Exam Question with Answer & Explanation

The correct answer is C: Project charter. Project Charter is developed in the Initiation Phase of a project, it is a brief formal document that outlines the project parameters.

Project Management Concepts

Question

A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP. Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?

Options

  • AMilestone chart
  • BWork breakdown structure
  • CProject charter
  • DDetailed scope statement

Explanation

Project Charter is developed in the Initiation Phase of a project, it is a brief formal document that outlines the project parameters.

Topics

#Project charter#Project initiation#Scope definition#Stakeholder communication