PK0-005 · Question #73

A severe adverse event was not documented and has impacted the project. Which of the following will be MOST affected?

The correct answer is D. Project schedule. An adverse event that goes undocumented means no risk response or corrective action was taken in time. The direct operational consequence is that tasks are delayed, resources are disrupted, and dependencies shift - all of which directly impact the project schedule. While communic

Project Management Concepts

Question

A severe adverse event was not documented and has impacted the project. Which of the following will be MOST affected?

Options

  • ACommunication plan
  • BProject charter
  • CAction item
  • DProject schedule

How the community answered

(59 responses)
  • A
    7% (4)
  • B
    3% (2)
  • C
    15% (9)
  • D
    75% (44)

Explanation

An adverse event that goes undocumented means no risk response or corrective action was taken in time. The direct operational consequence is that tasks are delayed, resources are disrupted, and dependencies shift - all of which directly impact the project schedule. While communication plans and other documents may need updating, the schedule is the artifact most concretely damaged by an unaddressed event that has already impacted the project.

Topics

#Risk management#Schedule management#Project impact#Project documentation