PK0-005 · Question #72
A project manager asks a project coordinator to put together a milestone report to present to the board of directors showing how the project has progressed in the last three months. The coordinator…
The correct answer is A. The document is too lengthy and includes extraneous details. A milestone report for a board of directors should be a high-level executive summary - concise, focused, and visually digestible. Boards need status, key achievements, risks, and decisions, not granular operational details. A 45-page document is far too lengthy for that…
Question
A project manager asks a project coordinator to put together a milestone report to present to the board of directors showing how the project has progressed in the last three months. The coordinator shares a 45-page document detailing all that has happened so far on the project. Which of the following is MOST likely the issue?
Options
- AThe document is too lengthy and includes extraneous details
- BThe document follows the appropriate template for a communication plan
- CThe document contains data that is aggregated for an executive review.
- DThe documents clear regarding the objectives and status, including graphs.
How the community answered
(39 responses)- A92% (36)
- B5% (2)
- C3% (1)
Explanation
A milestone report for a board of directors should be a high-level executive summary - concise, focused, and visually digestible. Boards need status, key achievements, risks, and decisions, not granular operational details. A 45-page document is far too lengthy for that audience and purpose, overwhelming executives with information they neither need nor have time to review. The core issue is that the coordinator produced an operational-level document rather than an executive-level summary, violating the principle of tailoring communication to the audience and purpose defined in the communication plan.
Topics