PK0-005 · Question #74
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
The correct answer is A. Issue log. The issue log is the correct tool here because the hurricane delay has already occurred - it is a realized problem, not a future risk. The issue log tracks active problems that need resolution and their impact on the project. A Gantt or milestone chart shows schedule timelines…
Question
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
Options
- AIssue log
- BGantt chart
- CMilestone chart
- DChange control log
How the community answered
(59 responses)- A75% (44)
- B3% (2)
- C8% (5)
- D14% (8)
Explanation
The issue log is the correct tool here because the hurricane delay has already occurred - it is a realized problem, not a future risk. The issue log tracks active problems that need resolution and their impact on the project. A Gantt or milestone chart shows schedule timelines but is not a documentation tool for problems. A change control log tracks approved changes to scope/schedule/cost, which would come later if the delay requires a formal change request.