nerdexam
CompTIA

PK0-005 · Question #75

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that w

The correct answer is B. Project management plan. Project management plan - developed in the planning phase and updated throughout project. Details how a project will be executed to achieve objectives.

Tools and documentation

Question

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options

  • AProject change management plan
  • BProject management plan
  • CProject transition plan
  • DProject communication plan

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    88% (30)
  • C
    3% (1)
  • D
    3% (1)

Explanation

Project management plan - developed in the planning phase and updated throughout project. Details how a project will be executed to achieve objectives.

Topics

#Project Planning#Stakeholder Engagement#Requirements Management#Project Management Plan

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice