PK0-005 · Question #63
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the
The correct answer is A. Allocate resources.. A complete project schedule requires not just task sequencing and durations, but also resource allocation - assigning specific people, equipment, or materials to each task. Without knowing who will do the work, the schedule cannot be finalized or realistic. Determining the projec
Question
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
Options
- AAllocate resources.
- BDetermine the project budget.
- CDevelop a communication plan.
- DEstablish baselines.
How the community answered
(45 responses)- A71% (32)
- B4% (2)
- C16% (7)
- D9% (4)
Explanation
A complete project schedule requires not just task sequencing and durations, but also resource allocation - assigning specific people, equipment, or materials to each task. Without knowing who will do the work, the schedule cannot be finalized or realistic. Determining the project budget and developing a communication plan are separate planning activities, not part of schedule development. Establishing baselines comes after the schedule is fully developed and approved, making resource allocation the missing step here.