PK0-005 · Question #64

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this inform

The correct answer is B. RACI. A RACI matrix (Responsible, Accountable, Consulted, Informed) is the standard tool for mapping project resources to their roles on each task. It clearly documents who does the work (Responsible), who owns the outcome (Accountable), who provides input (Consulted), and who is kept

Tools and documentation

Question

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options

  • ARFI
  • BRACI
  • CWBS
  • DSOW

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    96% (24)

Explanation

A RACI matrix (Responsible, Accountable, Consulted, Informed) is the standard tool for mapping project resources to their roles on each task. It clearly documents who does the work (Responsible), who owns the outcome (Accountable), who provides input (Consulted), and who is kept in the loop (Informed). An RFI (Request for Information) is used to gather information from vendors. A WBS (Work Breakdown Structure) decomposes deliverables, not assignments. A SOW (Statement of Work) defines scope for vendors or contractors.

Topics

#RACI matrix#Responsibility assignment#Project documentation#Resource management