PK0-005 · Question #62
The project sponsor informs the project manager that additional functionality must be added. Which of the following is the FIRST constraint to be updated?
The correct answer is C. Scope. When new functionality is requested, scope is the first constraint that must be updated because it defines what the project will deliver. Adding functionality is by definition a change to the project's scope. All other constraints-requirements (A), resources (B), and schedule (D)
Question
The project sponsor informs the project manager that additional functionality must be added. Which of the following is the FIRST constraint to be updated?
Options
- ARequirements
- BResources
- CScope
- DSchedule
How the community answered
(50 responses)- A4% (2)
- B2% (1)
- C84% (42)
- D10% (5)
Explanation
When new functionality is requested, scope is the first constraint that must be updated because it defines what the project will deliver. Adding functionality is by definition a change to the project's scope. All other constraints-requirements (A), resources (B), and schedule (D)-are downstream of scope. You cannot determine what new requirements are needed, what resources to add, or how long tasks will take until you first formally document the expanded scope. The scope change then triggers cascading updates to the other constraints through the integrated change control process.
Topics
Community Discussion
No community discussion yet for this question.