nerdexam
CompTIA

PK0-005 · Question #626

A project manager is working with the project team to bring the project planning phase to a close. As part of the closure process, the PMO requires an initial set of tasks, durations, predecessors…

The correct answer is A. Baseline. A baseline captures the approved initial plan for tasks, schedules, resources, and budgets, providing the reference point against which project performance and final outcomes are

Project Management Concepts

Question

A project manager is working with the project team to bring the project planning phase to a close. As part of the closure process, the PMO requires an initial set of tasks, durations, predecessors, resources, and budgets against which the project will be evaluated upon completion. Which of the following would be most appropriate to supply to the PMO to satisfy the requirement?

Options

  • ABaseline
  • BRBS
  • CWBS
  • DMilestones

How the community answered

(16 responses)
  • A
    75% (12)
  • B
    6% (1)
  • C
    13% (2)
  • D
    6% (1)

Explanation

A baseline captures the approved initial plan for tasks, schedules, resources, and budgets, providing the reference point against which project performance and final outcomes are

Topics

#Project Baselines#Project Planning#Performance Measurement#PMO Requirements

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice