PK0-005 · Question #626
A project manager is working with the project team to bring the project planning phase to a close. As part of the closure process, the PMO requires an initial set of tasks, durations, predecessors…
The correct answer is A. Baseline. A baseline captures the approved initial plan for tasks, schedules, resources, and budgets, providing the reference point against which project performance and final outcomes are
Question
A project manager is working with the project team to bring the project planning phase to a close. As part of the closure process, the PMO requires an initial set of tasks, durations, predecessors, resources, and budgets against which the project will be evaluated upon completion. Which of the following would be most appropriate to supply to the PMO to satisfy the requirement?
Options
- ABaseline
- BRBS
- CWBS
- DMilestones
How the community answered
(16 responses)- A75% (12)
- B6% (1)
- C13% (2)
- D6% (1)
Explanation
A baseline captures the approved initial plan for tasks, schedules, resources, and budgets, providing the reference point against which project performance and final outcomes are
Topics