A project manager decides to contract the development of an application through a traditional procurement process. Which of the following documents should the project manager complete first?

The correct answer is C. RFI. A request for information is completed first to gather high-level details about vendor capabilities, solutions, and market options, which helps the project manager refine requirements before issuing more specific procurement documents.

Tools and documentation

Question

A project manager decides to contract the development of an application through a traditional procurement process. Which of the following documents should the project manager complete first?

Options

  • ARFP
  • BRFB
  • CRFI
  • DRFQ

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    88% (21)
  • D
    4% (1)

Explanation

A request for information is completed first to gather high-level details about vendor capabilities, solutions, and market options, which helps the project manager refine requirements before issuing more specific procurement documents.

Topics

#procurement process#RFI#procurement documents#project contracting