PK0-005 · Question #625
A project manager decides to contract the development of an application through a traditional procurement process. Which of the following documents should the project manager complete first?
The correct answer is C. RFI. A request for information is completed first to gather high-level details about vendor capabilities, solutions, and market options, which helps the project manager refine requirements before issuing more specific procurement documents.
Question
A project manager decides to contract the development of an application through a traditional procurement process. Which of the following documents should the project manager complete first?
Options
- ARFP
- BRFB
- CRFI
- DRFQ
How the community answered
(24 responses)- A4% (1)
- B4% (1)
- C88% (21)
- D4% (1)
Explanation
A request for information is completed first to gather high-level details about vendor capabilities, solutions, and market options, which helps the project manager refine requirements before issuing more specific procurement documents.