A project team is working in an agile environment. Which of the following is the most accurate timing for communication with stakeholders?

The correct answer is D. Incrementally as features are ready. In an agile environment, stakeholders are engaged continuously through incremental delivery, allowing feedback and communication as features are completed rather than waiting for fixed reporting intervals.

Project Management Concepts

Question

A project team is working in an agile environment. Which of the following is the most accurate timing for communication with stakeholders?

Options

  • AOnce all of the features have been deployed
  • BDaily to discuss risks, issues, and status updates
  • CEvery week to provide status updates
  • DIncrementally as features are ready

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    6% (3)
  • C
    2% (1)
  • D
    89% (47)

Explanation

In an agile environment, stakeholders are engaged continuously through incremental delivery, allowing feedback and communication as features are completed rather than waiting for fixed reporting intervals.

Topics

#Agile communication#Stakeholder engagement#Agile methodologies#Incremental delivery