PK0-005 · Question #623
A PM is coordinating with the IT department to identify the staging environment maintenance windows in order to schedule testing around those times. Which of the following processes is described in…
The correct answer is C. Infrastructure change control. Coordinating maintenance windows with the IT department involves managing and aligning changes to shared infrastructure so testing does not conflict with system availability, which is part of infrastructure change control.
Question
A PM is coordinating with the IT department to identify the staging environment maintenance windows in order to schedule testing around those times. Which of the following processes is described in this scenario?
Options
- AContinuous deployment
- BCustomer notification
- CInfrastructure change control
- DAutomation testing
How the community answered
(45 responses)- A2% (1)
- B7% (3)
- C80% (36)
- D11% (5)
Explanation
Coordinating maintenance windows with the IT department involves managing and aligning changes to shared infrastructure so testing does not conflict with system availability, which is part of infrastructure change control.
Topics
Community Discussion