nerdexam
CompTIACompTIA

PK0-005 · Question #627

PK0-005 Question #627: Real Exam Question with Answer & Explanation

The correct answer is B: Perform root cause analysis.. After a temporary workaround is in place, the next step is to identify the underlying cause of the defect. Performing a root cause analysis ensures the team understands why the issue occurred so a permanent solution can be developed and future occurrences can be prevented.

Project Management Concepts

Question

After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?

Options

  • AProvide the change to the CCB.
  • BPerform root cause analysis.
  • CEscalate to the project steering committee.
  • DUpdate the risk register.

Explanation

After a temporary workaround is in place, the next step is to identify the underlying cause of the defect. Performing a root cause analysis ensures the team understands why the issue occurred so a permanent solution can be developed and future occurrences can be prevented.

Topics

#Defect Management#Root Cause Analysis#Quality Management#Problem Solving

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions