PK0-005 · Question #627
PK0-005 Question #627: Real Exam Question with Answer & Explanation
The correct answer is B: Perform root cause analysis.. After a temporary workaround is in place, the next step is to identify the underlying cause of the defect. Performing a root cause analysis ensures the team understands why the issue occurred so a permanent solution can be developed and future occurrences can be prevented.
Question
After releasing an application into production, a major defect is detected. The project team implements a work-around that fixes the issue for now. Which of the following should the team do next?
Options
- AProvide the change to the CCB.
- BPerform root cause analysis.
- CEscalate to the project steering committee.
- DUpdate the risk register.
Explanation
After a temporary workaround is in place, the next step is to identify the underlying cause of the defect. Performing a root cause analysis ensures the team understands why the issue occurred so a permanent solution can be developed and future occurrences can be prevented.
Topics
Community Discussion
No community discussion yet for this question.