PK0-005 · Question #573

A highly scored negative causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

The correct answer is A. Execute the contingency plan.. A risk trigger indicates that the conditions for a risk to occur are present. Since this risk was already identified and planned for, the appropriate next step is to execute the contingency plan before the issue fully materializes.

Project Management Concepts

Question

A highly scored negative causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

Options

  • AExecute the contingency plan.
  • BPerform a work-around.
  • CEscalate to senior management.
  • DAssign a risk owner.

How the community answered

(38 responses)
  • A
    76% (29)
  • B
    5% (2)
  • C
    16% (6)
  • D
    3% (1)

Explanation

A risk trigger indicates that the conditions for a risk to occur are present. Since this risk was already identified and planned for, the appropriate next step is to execute the contingency plan before the issue fully materializes.

Topics

#Risk Management#Contingency Plan#Risk Response#Project Execution