PK0-005 · Question #575
PK0-005 Question #575: Real Exam Question with Answer & Explanation
The correct answer is C: The team is unclear which meetings they should attend.. The communication plan defines how, when, and to whom information is distributed. If team members are uncertain about meeting expectations, the communication plan must be revised to clarify responsibilities and ensure effective information flow.
Question
Which of the following situations would require a project manager to revise the communication plan during a project's execution?
Options
- AA change is approved that impacts the project schedule and budget.
- BThe test results are not as expected.
- CThe team is unclear which meetings they should attend.
- DA stakeholder requests some changes to the scope.
Explanation
The communication plan defines how, when, and to whom information is distributed. If team members are uncertain about meeting expectations, the communication plan must be revised to clarify responsibilities and ensure effective information flow.
Topics