PK0-005 · Question #571

PK0-005 Question #571: Real Exam Question with Answer & Explanation

The correct answer is A: Document the change request in the change log.. The first step when a stakeholder requests a new feature is to formally document the change request in the change log. This ensures it enters the change control process for proper review, impact assessment, and approval before any action is taken.

Project Management Concepts

Question

A company is designing a new ERP system. The SOW includes modules for different departments. During a meeting, a stakeholder requests an additional feature. Which of the following actions should the project manager should take next?

Options

  • ADocument the change request in the change log.
  • BCommunicate the change request to stakeholders.
  • CDetermine the decision makers for the change request.
  • DValidate the change request.

Explanation

The first step when a stakeholder requests a new feature is to formally document the change request in the change log. This ensures it enters the change control process for proper review, impact assessment, and approval before any action is taken.

Topics

#Change Management#Change Request#Project Manager Role#Change Log