PK0-005 · Question #564
A project manager is running a DevOps project in two-week sprints. Given the following information: Which of the following is the number of issues logged during the second sprint?
The correct answer is B. 7. This question references an external chart or table (not reproduced here) showing cumulative or per-sprint issue counts. Based on the data provided in the original exhibit, the second sprint logged 7 issues. In sprint-based tracking, issues logged per sprint can be read from a…
Question
A project manager is running a DevOps project in two-week sprints. Given the following information:
Which of the following is the number of issues logged during the second sprint?
Exhibit
Options
- A6
- B7
- C8
- D9
How the community answered
(48 responses)- A2% (1)
- B96% (46)
- C2% (1)
Explanation
This question references an external chart or table (not reproduced here) showing cumulative or per-sprint issue counts. Based on the data provided in the original exhibit, the second sprint logged 7 issues. In sprint-based tracking, issues logged per sprint can be read from a sprint backlog, burndown chart, or issue log by identifying entries created or opened during the second sprint's date range. The correct value derived from the exhibit is 7.