Project Management Concepts
Question
Project stakeholders are concerned that a project might not finish on time due to previous slippage. Which of the following is the best way for the project manager to determine how much longer the project will take, assuming the project team will continue to work at the current production rate?
Options
- AEstimate by using the baseline divided by the schedule performance index for critical path tasks.
- BReport the budgeted cost of work scheduled and the budgeted cost of work performed.
- CAsk an external consultant for their projection based on experience and industry standards.
- DAssess the schedule reserves to determine if it is adequate for the remaining risk.
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Earned Value Management (EVM)#Schedule Performance Index (SPI)#Project forecasting#Schedule management