CompTIACompTIA
PK0-005 · Question #562
PK0-005 Question #562: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-005 to reveal the answer and full explanation for question #562. The question stem and answer options stay visible for context.
Project Life Cycle Phases
Question
During the planning phase, a project manager decides to introduce a new enterprise portal toot, which has been approved by the PMO. Which of the following should be the project manager's next step?
Options
- ACreate a transition plan.
- BAdd training to the schedule.
- CUpdate the project charter
- DInvolve the CCB.
Unlock PK0-005 to see the answer
You've previewed enough free PK0-005 questions. Unlock PK0-005 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project Planning#Training Management#New Tool Adoption#Schedule Management