During the planning phase, a project manager decides to introduce a new enterprise portal toot, which has been approved by the PMO. Which of the following should be the project manager's next step?
The correct answer is B. Add training to the schedule. Once the new tool is approved by the PMO, the project manager’s next step is to ensure the team can use it effectively. Adding training to the schedule prepares the team for adoption and successful integration into the project workflow.
Question
During the planning phase, a project manager decides to introduce a new enterprise portal toot, which has been approved by the PMO. Which of the following should be the project manager's next step?
Options
- ACreate a transition plan.
- BAdd training to the schedule.
- CUpdate the project charter
- DInvolve the CCB.
How the community answered
(47 responses)- A4% (2)
- B87% (41)
- C2% (1)
- D6% (3)
Explanation
Once the new tool is approved by the PMO, the project manager’s next step is to ensure the team can use it effectively. Adding training to the schedule prepares the team for adoption and successful integration into the project workflow.