Project Life Cycle Phases

Question

During the planning phase, a project manager decides to introduce a new enterprise portal toot, which has been approved by the PMO. Which of the following should be the project manager's next step?

Options

  • ACreate a transition plan.
  • BAdd training to the schedule.
  • CUpdate the project charter
  • DInvolve the CCB.