As part of the planning phase for a new project, a team needs to create a fixed point to compare progress against in order to monitor alignment with initial cost, schedule, and scope. Which of the…
The correct answer is A. Baseline. A baseline is the fixed reference point established during project planning for cost, schedule, and scope. It serves as the standard against which project performance is measured to track variances and ensure alignment with the plan.
Question
As part of the planning phase for a new project, a team needs to create a fixed point to compare progress against in order to monitor alignment with initial cost, schedule, and scope. Which of the following would be the best for the team to create?
Options
- ABaseline
- BMilestones
- CGantt chart
- DProject charter
How the community answered
(56 responses)- A93% (52)
- B2% (1)
- C2% (1)
- D4% (2)
Explanation
A baseline is the fixed reference point established during project planning for cost, schedule, and scope. It serves as the standard against which project performance is measured to track variances and ensure alignment with the plan.