PK0-005 · Question #560

After a project's completion, the project manager and the executive leadership team decide to reward the team. Which of the following documents should the PM and the executive leadership team review…

The correct answer is D. Organizational ethics policy. Before giving rewards, the project manager and leadership must ensure that recognition and incentives align with the organization’s ethics policy. This prevents favoritism, bias, or actions that could violate ethical standards.

Basics of IT and governance

Question

After a project's completion, the project manager and the executive leadership team decide to reward the team. Which of the following documents should the PM and the executive leadership team review before determining rewards?

Options

  • AStatement of work
  • BRules of engagement
  • CProject scope statement
  • DOrganizational ethics policy

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    12% (4)
  • C
    6% (2)
  • D
    79% (26)

Explanation

Before giving rewards, the project manager and leadership must ensure that recognition and incentives align with the organization’s ethics policy. This prevents favoritism, bias, or actions that could violate ethical standards.

Topics

#Organizational ethics#Project rewards#Organizational policies#Governance