nerdexam
CompTIACompTIA

PK0-005 · Question #482

PK0-005 Question #482: Real Exam Question with Answer & Explanation

The correct answer is C: Compromise. By negotiating a middle ground, the PM used compromise as a conflict resolution technique. Force and avoid do not build consensus, while smoothing minimizes issues but does not resolve them. Compromise achieves agreement acceptable to both sides.

Project Management Concepts

Question

During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?

Options

  • AForce
  • BSmooth
  • CCompromise
  • DAvoid

Explanation

By negotiating a middle ground, the PM used compromise as a conflict resolution technique. Force and avoid do not build consensus, while smoothing minimizes issues but does not resolve them. Compromise achieves agreement acceptable to both sides.

Topics

#Stakeholder management#Conflict resolution#Negotiation#Deliverable approval

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions