PK0-005 · Question #482
During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes…
The correct answer is C. Compromise. By negotiating a middle ground, the PM used compromise as a conflict resolution technique. Force and avoid do not build consensus, while smoothing minimizes issues but does not resolve them. Compromise achieves agreement acceptable to both sides.
Question
During a phase review, two stakeholders discuss the approval of a deliverable. The project manager convinces the stakeholders to agree on a common solution. Which of the following best describes what the project manager did to gain approval from both stakeholders?
Options
- AForce
- BSmooth
- CCompromise
- DAvoid
How the community answered
(37 responses)- A3% (1)
- B11% (4)
- C81% (30)
- D5% (2)
Explanation
By negotiating a middle ground, the PM used compromise as a conflict resolution technique. Force and avoid do not build consensus, while smoothing minimizes issues but does not resolve them. Compromise achieves agreement acceptable to both sides.