PK0-005 · Question #483

Which of the following are considered core elements in a project closeout report?

The correct answer is B. Project scope, schedule, and cost D. Results and outcomes of the project. Project scope, schedule, and cost are core elements in a project closeout report because they summarize how well the project performed against the original plan. Results and outcomes of the project are essential to document whether the project met its objectives and delivered…

Tools and documentation

Question

Which of the following are considered core elements in a project closeout report?

Options

  • AGap analysis of critical path
  • BProject scope, schedule, and cost
  • CCompany vision, mission, and goals
  • DResults and outcomes of the project

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    90% (43)
  • C
    4% (2)

Explanation

Project scope, schedule, and cost are core elements in a project closeout report because they summarize how well the project performed against the original plan. Results and outcomes of the project are essential to document whether the project met its objectives and delivered the intended value.

Topics

#Project closeout report#Project documentation#Project success metrics#Project outcomes