nerdexam
CompTIACompTIA

PK0-005 · Question #484

PK0-005 Question #484: Real Exam Question with Answer & Explanation

The correct answer is A: Contingency reserves. Contingency reserves are time or budget buffers set aside to address unforeseen issues. By using time-based contingency reserves, the project manager can slow down the project pace (e.g., approve time off) without affecting the overall project deadline, thus helping to mitigate

Project Management Concepts

Question

During an important stage of a project, a project team is suffering from burnout, which is impacting the quality of the work. The project manager analyzes the feasibility of approving additional time off. Which of the following will allow the project manager to reduce the pace of the work to mitigate these concerns?

Options

  • AContingency reserves
  • BEscalation to the steering committee
  • CBacklog prioritization
  • DCritical path

Explanation

Contingency reserves are time or budget buffers set aside to address unforeseen issues. By using time-based contingency reserves, the project manager can slow down the project pace (e.g., approve time off) without affecting the overall project deadline, thus helping to mitigate

Topics

#Contingency reserves#Risk management#Schedule management#Team management

Community Discussion

No community discussion yet for this question.

Full PK0-005 PracticeBrowse All PK0-005 Questions