PK0-005 Question #480: Real Exam Question with Answer & Explanation
The correct answer is B: A plan for avoiding potential issues that may arise during project execution. The team is leveraging lessons learned to create a preventive plan for avoiding issues in the upcoming project enhancement. This falls under risk management and compliance, ensuring previous failures do not repeat.
Question
A project manager is taking notes along with gathering feedback about a prior project in order to consider known issues with a project enhancement. Which of the following best describes the plan that the project team is working on?
Options
- AA plan for capturing issues and conflicts in a project's knowledge base
- BA plan for avoiding potential issues that may arise during project execution
- CA plan for documenting the outcomes of the project
- DA plan for addressing and resolving identified issues once the project has been completed
Explanation
The team is leveraging lessons learned to create a preventive plan for avoiding issues in the upcoming project enhancement. This falls under risk management and compliance, ensuring previous failures do not repeat.