nerdexam
CompTIA

PK0-005 · Question #459

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

The correct answer is C. Communicate to the stakeholders. When a change request is rejected due to a code freeze, the project manager should communicate to the stakeholders to inform them of the situation. Transparent communication ensures that all parties are aware of the project's current status and any limitations affecting…

Project Management Concepts

Question

A project manager submits a change request. The change request is rejected because of code freeze. Which of the following actions should the project manager take next?

Options

  • AUpdate the risk register.
  • BEscalate the issue for exceptional approval.
  • CCommunicate to the stakeholders.
  • DSubmit a duplicate change request.

How the community answered

(27 responses)
  • A
    7% (2)
  • C
    89% (24)
  • D
    4% (1)

Explanation

When a change request is rejected due to a code freeze, the project manager should communicate to the stakeholders to inform them of the situation. Transparent communication ensures that all parties are aware of the project's current status and any limitations affecting progress. This step is crucial for managing expectations and maintaining stakeholder trust.

Topics

#Change Management#Stakeholder Communication#Project Manager Responsibilities

Community Discussion

No community discussion yet for this question.

Full PK0-005 Practice